Cambodian Stung Russei Downstream Hydro-Power Dam Project
Type : Excavator
Date of Release : 2012-11-15


Project capacity: The terminal layout is a roller compacted concrete gravity dam. Normal impounded level: 108m. Maximum dam height: 58.5m.

Totawl ater turbine-generator sets Installed capacity: 132MW (with two 66-MV mixed-flow The bidden section started from diversion tunnel excavation in October 2010; the dam-off engineering will be finished by the end of October 2011; the dam will be completed by the end of December 2012; the lower gate of diversion tunnel will be closed in the middle of March 2013; the two generator sets will be put into operation by the end of June in the same year.





 